TELEICU/Change management

From OHC Network Wiki
Revision as of 08:40, 6 July 2026 by Admin (talk | contribs) (Automated edit (via update-page on MediaWiki MCP Server))
guideteleicuCARE 3.0+

Process for planning, reviewing, and deploying changes across the TELEICU fleet.

Change lifecycle

{{#mermaid:flowchart LR
    PLAN["Plan<br/>(RFC document)"]
    PR["Pull Request<br/>(git)"]
    REVIEW["Review<br/>(peer + hub admin)"]
    STAGING["Staging<br/>(test env)"]
    CANARY["Canary<br/>(1-2 sites)"]
    ROLLOUT["Regional Rollout"]
    DONE["Fleet-wide"]

    PLAN --> PR
    PR --> REVIEW
    REVIEW --> STAGING
    STAGING --> CANARY
    CANARY --> ROLLOUT
    ROLLOUT --> DONE
    CANARY -->|"fail → revert"| PLAN
    ROLLOUT -->|"fail → pause"| PLAN
}}

Change types

| Type | Review required | Staging | Canary | Rollout window | |---|---|---|---|---| | Security patch | Light (1 reviewer) | Yes | 1 site | Within 7 days | | Bug fix | Normal (2 reviewers) | Yes | 1 site | Next business day | | Feature/middleware update | Full (2 reviewers + hub lead) | Yes | 2 sites | Scheduled window | | OS update (NixOS flake) | Full (2 reviewers) | Yes | 2 sites | Quarterly | | Hardware change | Site-specific | N/A | N/A | As needed | | Emergency patch | Post-hoc review | Bypassed | Bypassed | Immediate |

RFC template

Every change should document:

  • What is changing and why
  • Risk assessment — what could break
  • Rollback plan — how to undo
  • Impact scope — which sites/nodes are affected
  • Testing performed — what was validated in staging
  • Monitoring — what to watch during rollout

Approval gates

  1. Peer review (code/infra team)
  2. Hub admin sign-off (if clinical impact is possible)
  3. Ops lead approval for fleet-wide rollout