TELEICU/Change management

From OHC Network Wiki
guideteleicuCARE 3.0+

Process for planning, reviewing, and deploying changes across the TELEICU fleet.

Change lifecycle

Change types

Type Review required Staging Canary Rollout window
Security patch Light (1 reviewer) Yes 1 site Within 7 days
Bug fix Normal (2 reviewers) Yes 1 site Next business day
Feature/middleware update Full (2 reviewers + hub lead) Yes 2 sites Scheduled window
OS update (NixOS flake) Full (2 reviewers) Yes 2 sites Quarterly
Hardware change Site-specific N/A N/A As needed
Emergency patch Post-hoc review Bypassed Bypassed Immediate

RFC template

Every change should document:

  • What is changing and why
  • Risk assessment — what could break
  • Rollback plan — how to undo
  • Impact scope — which sites/nodes are affected
  • Testing performed — what was validated in staging
  • Monitoring — what to watch during rollout

Approval gates

  1. Peer review (code/infra team)
  2. Hub admin sign-off (if clinical impact is possible)
  3. Ops lead approval for fleet-wide rollout